Wednesday, November 02, 2022

Stage 1 - and 2 load shedding until Friday

Eskom has announced that it will rotate between Stage 1 - and Stage 2 load shedding until Friday.

In a statement, the ailing parastatal said loadshedding will continue to be implemented on a daily basis at 16:00 – 05:00, and Stage 1 loadshedding will then be implemented daily at 05:00 – 16:00

‘’The increase in loadshedding is mainly due to the need to preserve emergency generation reserves, the delay in returning four generating units to service while many running units are operating at reduced capacity due to technical faults,’’ said spokesperson, Sikonathi Manthantsha.

‘’The delay in the return of two generating units at Camden, one unit each at Kendal and Matimba power stations have contributed to the generation capacity shortages,’’ he added.

Meanwhile, the City of Cape Town said its customers will only experience Stage 2 rolling power cuts between 10p.m and 5a.m

 

PICTURE: CoCT

Done By: Mitchum George

No comments:

DA retains seat in Manenberg

The Democratic Alliance (DA) retained its seat in ward 30 in the Cape Metro . A municipal by-elections was held for the ward on Tuesday an...