By Mikhaila Crowie
25 April 2009
The fitting of the Green Point Stadium’s glass roof, will get underway on Monday, after the inner tension ring was raised two months ago.
The City of Cape Town’s technical director for 2010 David Hugo, said everything is going as schedule.
The glass structure, made of laminated sheets 16mm thick, will weigh 1 500 tons and fill an area of 37sq km.
Engineers hope to finished with the roof construction in September.
The roof has been constructed in New York by Birdair, the famed stadium roofing company and designed by German architectural firm GMP Architects.
Subscribe to:
Post Comments (Atom)
Fewer people driving and texting, but number still high
Fewer people are using their phones whilst driving. This is according to the City of Cape Town who revealed that cellphone impounds dropped ...

-
A man suspected of killing and raping a number of members of the farm worker community in Philippi on the Cape Flats appears in a Cape Town ...
-
''Human behaviour is the main cause of wildfires.'' These remarks were made by the Western Cape’s Local Government, Environm...
No comments:
Post a Comment